NEW QUESTION # 39
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

  • A. The person responsible for the network activity
  • B. The person responsible for the work center
  • C. The MRP controller for the network
  • D. The person responsible for the superior WBS element

Answer: C


NEW QUESTION # 40
In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

  • A. Scheduling and capacity category
  • B. Capacity planner group in the network header
  • C. Control key of an activity
  • D. Scheduling and distribution key

Answer: D


NEW QUESTION # 41
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.

  • A. Duration
  • B. Profit center
  • C. Work
  • D. Activity type

Answer: C,D


NEW QUESTION # 42
Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question

  • A. Activities with the time constraint "Must start on" always have a negative float time
  • B. The float time of WBS elements is calculated by extrapolation
  • C. Float time can be negative
  • D. The maximum size of a free float is as large as the total float of an activity
  • E. By default, critical activities have a float time, which is less than or equal to zero

Answer: A,C,D


NEW QUESTION # 43
Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board.
Note : there are 3 correct answers for this question.

  • A. Display of project -relevant purchase order.
  • B. Using specific color management for Gantt Chart.
  • C. Display of production orders assigned to WBS element.
  • D. Display of plant maintenance orders for activities.
  • E. Display of project cost plan.

Answer: C,D,E


NEW QUESTION # 44
Revenues & Payment
A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?

  • A. Split the project intdifferent project according to each company code.
  • B. Settle the WBS element to the highest billing element before you do the result analysis.
  • C. Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.
  • D. Change the project structure so that it correspond better to the company's organization structure.

Answer: D


NEW QUESTION # 45
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.

  • A. Resource
  • B. Location
  • C. Production version
  • D. Material

Answer: A,B


NEW QUESTION # 46
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question

  • A. Project versions can be created automatically based on user status
  • B. Manually Created project versions always require a project version profile
  • C. Project versions are mandatory for Milestone Trend Analysis (MTA)
  • D. Project versions can be changed

Answer: A,C


NEW QUESTION # 47
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question

  • A. The procurement type of the material must be internal
  • B. The materials must allow sales order or project stock
  • C. An MRP group must be assigned
  • D. The exact lot size procedure must be used

Answer: A,D


NEW QUESTION # 48
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.

  • A. Automatic activation with budget assignment
  • B. Background activation (CJBV - Activate Availability Control)
  • C. Automatic activation with assignment to an investment program
  • D. Automatic activation with the first actual posting

Answer: A,B


NEW QUESTION # 49
You are working with networks and WBS elements. Which of the following statements applies

  • A. You can assign the network header to multiple WBS elements
  • B. You can reassign an activity from one network to another
  • C. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
  • D. You have to maintain a network profile in the project profile

Answer: C


NEW QUESTION # 50
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

  • A. Easy Cost Planning
  • B. Schedule Manager
  • C. Project Builder
  • D. Project planning board

Answer: C,D


NEW QUESTION # 51
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?

  • A. Requirements class
  • B. Schedule line category
  • C. Item category
  • D. Requirements type

Answer: C


NEW QUESTION # 52
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?

  • A. Missing material availability
  • B. Missing budget for material components
  • C. Missing reservations for material components
  • D. Missing authorizations to release material components

Answer: D


NEW QUESTION # 53
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.

  • A. Relationships can be used to connect activities of different networks.
  • B. A network activity can be assigned to several WBS elements.
  • C. A network can be activity-account-assigned and header-account-assigned.
  • D. Material components can be assigned to activity elements.

Answer: A,C


NEW QUESTION # 54
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question

  • A. Assignment between material and standard network
  • B. A bill of material with sales views
  • C. A material master with sales views
  • D. A production order
  • E. Standard network with activities

Answer: A,C,E


NEW QUESTION # 55
You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question

  • A. Profit center
  • B. Duration
  • C. Work
  • D. Activity type

Answer: B,C


NEW QUESTION # 56
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

  • A. Enter 10 days as duration.
  • B. Enter an offset of 10 days to the start date of the activity.
  • C. Enter an offset of -18 days to the finish date of the activity.
  • D. Enter February 10 as fixed date.

Answer: D


NEW QUESTION # 57
Project structure
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.

  • A. Project definition
  • B. Standard network
  • C. Project version.
  • D. Standard Project definition
  • E. Project milestone

Answer: B,C,D


NEW QUESTION # 58
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.

  • A. Saving a supplier invoice
  • B. Saving a purchase order
  • C. Saving a goods receipt
  • D. Saving a service entry sheet

Answer: C,D


NEW QUESTION # 59
......


The SAP C-TS412-2021 exam is an excellent opportunity for professionals who are interested in advancing their careers in the field of SAP S/4HANA Project Systems. Successful candidates gain a competitive edge in the job market, as they are recognized as experts in the field. Additionally, the certification provides a formal recognition of the candidate's skills and knowledge, which can lead to increased credibility and better job opportunities.

 