NEW QUESTION # 29
Which of the following will not be in Issue register?
- A. How issues will be identified, captured and assessed
- B. Date issue was raised
- C. Description of issue
- D. Categorization of issue
Answer: A
Explanation:
The process of how issues will be identified, captured, and assessed is not recorded in the Issue Register itself but is instead documented in the Issue Management Strategy.
The MSP Practitioner clarifies: "How to deal with issue is identified in issue management strategy," meaning the register contains actual issues with details such as date raised, description, and categorization but not the procedural approach.
This distinction ensures that the register remains a real-time log of current issues while the management strategy defines policies and processes for consistent issue handling across the programme.
Maintaining this separation improves clarity and operational efficiency in issue management.
NEW QUESTION # 30
Which of the following statements is FALSE?
- A. The SRO is appointed by the Sponsoring Group.
- B. The SRO acts as the Project Executive on all the Project Boards.
- C. The SRO is likely to be a peer of the Sponsoring Group.
- D. The SRO must have enough seniority to take on accountability for the programme delivery.
Answer: B
Explanation:
The false statement here is that the SRO acts as the Project Executive on all the Project Boards. The MSP Practitioner explicitly clarifies that the SRO does not take on this project-level responsibility. Instead, the SRO's role is to provide overall accountability for the programme and to ensure the programme delivers its intended outcomes and benefits.
The SRO holds a senior position with enough authority to make decisions and secure resources and is typically a peer of the Sponsoring Group to ensure alignment with corporate strategy. The Sponsoring Group appoints the SRO to oversee the programme's governance and delivery effectively.
Project Executives, in contrast, represent individual projects within the programme and report to the SRO via the programme governance structure. They focus on delivering specific project outputs, while the SRO's responsibility is to coordinate these efforts to achieve strategic benefits.
This distinction is vital to MSP's governance architecture: it prevents the SRO from being burdened with operational project detail, allowing focus on strategic oversight, stakeholder engagement, and benefit realization.
The MSP Practitioner states: "SRO doesn't act as a project representative," underscoring the clear division between programme and project governance to maintain effective control and leadership throughout the programme lifecycle.
NEW QUESTION # 31
Which of the following is a critical organizational element?
- A. Delivery mechanisms for change
- B. Stakeholder engagement
- C. Leading change
- D. Quality management and assurance
Answer: A
NEW QUESTION # 32
Who approves Business Case?
- A. Sponsoring Group
- B. Programme Manager
- C. BCM
- D. SRO
Answer: D
Explanation:
The Senior Responsible Owner (SRO) approves the Business Case and is accountable for ensuring it remains valid and aligned with strategic objectives.
The MSP Practitioner states: "SRO approves (as he is accountable for it)." This underscores the SRO's critical role in governing programme justification and ensuring investment decisions remain sound.
While the Sponsoring Group may endorse or sponsor the programme, formal accountability and approval for the Business Case rest with the SRO, ensuring clear responsibility for delivery against agreed benefits.
This accountability helps maintain control and confidence in programme investment and delivery.
NEW QUESTION # 33
Programme needs to create a working environment that is both robust and flexible enough to be able to cope with frequent and sometimes radical changes of boundary. Which programme management principle suggests this?
- A. Remaining aligned with corporate strategy
- B. Envisioning and communicating better future
- C. Leading change
- D. Adding value
Answer: A
NEW QUESTION # 34
Which of the following is NOT set out by the Programme Brief?
- A. Key resources needed
- B. Analysis of the options available
- C. Estimated cost
- D. Risks and issues
Answer: B
NEW QUESTION # 35
Which of following is input for 'managing the tranches'?
- A. Approval to proceed
- B. Programme Brief
- C. Programme preparation plan
- D. Assurance review reports
Answer: A
Explanation:
Approval to proceed is a critical input for the 'Managing the Tranches' process. Without formal approval, the programme cannot move into tranche delivery phases. The MSP Practitioner specifies: "Without approval to proceed, programme will not enter this process." This highlights the formal gating and control process essential for structured programme progression.
NEW QUESTION # 36
Which one of below options is the delivery mechanism for 'stakeholder engagement'?
- A. Programme communications plan
- B. Resource management plan
- C. Benefit profiles
- D. Information management plan
Answer: A
NEW QUESTION # 37
The programme is in the first tranche. The programme manager met with the project managers from the Employment Contracts and Call Centre Rationalization projects as well as the BCM. Many topics were discussed. After the meeting, the programme manager reviewed the information gathered at the meeting.
Which information should result in an addition to the risk register?
- A. Due to staff sickness, the Call Centre Rationalization Project is delayed in delivering the call centre integration, but the project is expected to finish on time
- B. Customer service staff will be trained on all call centre systems in order to answer calls from customers and cross-sell all of UU's products
- C. Currently customer service staff have specialist areas of expertise in either electricity, gas or water and do not answer calls from other customers
- D. Tranche 3 could be delayed as the Customer Processes Project has not yet started, and it is unclear what training the call centre staff will need
Answer: D
Explanation:
Comprehensive and Detailed 200 to 250 words of Explanation From Exact Extract of project- programme-and-portfolio-management of 5th Edition MSP:
In MSP 5th Edition, a Risk is defined as an uncertain event or set of events that, should it occur, will have an effect on the achievement of objectives. The Risk Register is used to capture these uncertainties. It is vital to distinguish between a "risk" (uncertainty about the future) and an "issue" (something that has already happened or a current fact).
Option C represents a classic programme risk: there is uncertainty regarding the training requirements for a future project, which creates a potential threat to the timeline of Tranche 3. This uncertainty needs to be managed, analyzed, and mitigated, making it a perfect entry for the risk register.
* Option A describes a planned outcome or benefit.
* Option B describes the current "as-is" state (a fact).
* Option D describes a project-level issue (staff sickness and delay) that the project manager expects to resolve. While it could be escalated, the inherent uncertainty regarding the future impact on Tranche 3 in Option C is a more fundamental programme-level risk that must be recorded and tracked.
NEW QUESTION # 38
Which of the following is a critical organizational element?
- A. Delivery mechanisms for change
- B. Stakeholder engagement
- C. Leading change
- D. Quality management and assurance
Answer: A
Explanation:
The critical organizational elements in MSP include Corporate strategy, Delivery mechanisms for change, and the Business as usual environment. Delivery mechanisms for change refer to the structures and processes organizations use to implement and manage changes introduced by programmes. These elements are foundational to effective governance and ensure alignment with strategic objectives. Other options like Leading change and Stakeholder engagement are important but classified differently within MSP's framework.
NEW QUESTION # 39
Who has the responsibility for monitoring the progress of benefits realization against the plan?
- A. Business Change Manager
- B. Programme Office
- C. Senior Responsible Owner
- D. Programme Manager
Answer: A
Explanation:
The Business Change Manager (BCM) holds the primary responsibility for monitoring the progress of benefits realization against the plan. This role is focused on ensuring that the expected benefits from the programme's outputs and outcomes are actually realized in the business environment. The BCM works closely with stakeholders, operational managers, and programme teams to track benefit achievement, resolve issues that might impede benefit delivery, and report progress.
According to the MSP Practitioner: "BCM is responsible for monitoring benefits." This accountability includes validating that the changes introduced by the programme are embedded within business operations and are delivering measurable value as outlined in the Benefits Realization Plan. The BCM must maintain a clear line of sight on benefits, manage dependencies between projects and operational teams, and oversee any transition activities required to sustain benefits.
The Programme Manager and Senior Responsible Owner (SRO) have broader accountability for programme delivery and governance, but it is the BCM who acts as the day-to-day custodian of benefits. They translate strategic benefit objectives into operational terms and ensure the organisation adapts to new ways of working.
This ensures that benefits do not remain theoretical but are tangibly realized, measured, and maximized over time.
Effective benefits monitoring by the BCM mitigates the risk of programmes delivering outputs that do not translate into business improvements or strategic value, reinforcing MSP's emphasis on outcome-focused delivery.
NEW QUESTION # 40
UU has always used a linear project management methodology in the past with varying degrees of success.
During the 'design the outcomes' process, UU has decided to trial an agile approach to deliver projects throughout Tranche 1.
Which theme is being applied to the 'design the outcomes' process?
- A. The 'decisions' theme is being applied by coming to a conclusive decision to use an agile approach for delivery
- B. The 'knowledge' theme is being applied by making use of lessons from their previous agile projects
- C. The 'design' theme is being applied by deliberately designing the work to make use of an iterative approach
- D. The 'structure' theme is being applied by using an agile delivery method to a complex piece of work
Answer: C
Explanation:
Comprehensive and Detailed 200 to 250 words of Explanation From Exact Extract of project- programme-and-portfolio-management of 5th Edition MSP:
The Design Theme in MSP 5th Edition is not limited to the technical architecture of the solution; it also encompasses the design of the delivery approach and the path to the future state. According to the MSP 5th Edition guidance, during the 'Design the outcomes' process, the programme must determine the most effective lifecycle for its constituent projects and workstreams. This involves deciding whether a linear, iterative (agile), or hybrid approach is most suitable for the nature of the change.
In this scenario, UU's decision to trial an agile approach is a fundamental design choice. Option D is the correct answer because the Design Theme is responsible for defining how the programme will transition from the current state to the target operating model. By choosing an iterative approach, the programme is
"designing" the work to allow for rapid feedback, flexibility, and incremental value delivery. While this decision involves a "choice" (Option B), the MSP framework specifically categorizes the selection of delivery methodologies and lifecycles under the Design Theme because it shapes the entire strategy for how the outcomes will be realized. This alignment ensures that the delivery method matches the complexity and uncertainty of the programme's objectives, which is a key requirement of the Design Theme's focus on creating a viable and effective blueprint for transformation.
NEW QUESTION # 41
Which of the following is NOT normally a characteristic of the Vision Statement?
- A. It must describe a desirable future
- B. It is short
- C. Key benefits are implicit
- D. It must be time dependent
Answer: D
NEW QUESTION # 42
Which of the following is not correct about 'Leading change'?
- A. Get approval from sponsoring group
- B. Create novel solutions to problems
- C. Actively engage stakeholder
- D. Appoint right people at right time
Answer: A
NEW QUESTION # 43
Which document has the as-is state of organization?
- A. Programme Plan
- B. Blueprint
- C. Business Case
- D. Vision
Answer: B
Explanation:
The Blueprint document defines both the as-is and to-be (future) states of the organization. It provides a detailed description of the current operational environment and the changes required to achieve the programme's desired outcomes.
The MSP Practitioner explains: "Blueprint defines as-is and future state of organization," serving as a key governance document to guide design and delivery of the transformation.
By articulating the current state clearly, the Blueprint helps identify gaps, dependencies, and change requirements, ensuring that the programme's outputs align with the intended future state, thus supporting successful transformational change.
NEW QUESTION # 44
Which of following Best defines capital cost?
- A. Costs associated to roles for programme management
- B. Cost of fixed assets
- C. Cost of BCM and change team
- D. Costs of activities associated in realizing the benefits
Answer: B
NEW QUESTION # 45
Which of following is input for 'managing the tranches'?
- A. Approval to proceed
- B. Programme Brief
- C. Programme preparation plan
- D. Assurance review reports
Answer: A
NEW QUESTION # 46
The programme is halfway through the first tranche. The CRO has contacted the programme manager with exciting news. They have been shown a new piece of technology which makes it easier and cheaper to service and maintain smart meters. They think that it might be possible to add this technology to future smart water meter installations without much additional cost. The programme manager has added this to the risk register.
Is this an appropriate application of the design' theme, and why?
- A. Yes, because if smart meter installations include this technology then future maintenance costs could be reduced
- B. No, because the possibility of reducing maintenance costs should be treated as an issue and action taken immediately
- C. No, because reduced maintenance costs should be added to the benefits map as a new benefit of the programme
- D. Yes, because changing the existing installation plan could bring uncertainty to the programme and should be avoided
Answer: A
Explanation:
Comprehensive and Detailed 200 to 250 words of Explanation From Exact Extract of project- programme-and-portfolio-management of 5th Edition MSP:
The Design Theme in MSP 5th Edition focuses on defining the "future state" and the path to get there. This involves the Vision, the Benefit Map, and the Target Operating Model (TOM). However, the design is not fixed; it must be open to improvements that enhance the programme's value. In risk management, a "risk" can be either a threat or an opportunity.
In this scenario, the new technology represents an opportunity-an uncertain event that would have a positive impact on objectives (reducing maintenance costs). Option A is correct because adding this opportunity to the risk register allows the programme to evaluate whether it should be "exploited" or
"enhanced." This is a correct application of the Design Theme because it relates to a potential change in the technical design of the programme's output (the smart meters) to deliver better value. By recording it in the risk register, the programme manager ensures it is formally assessed for its impact on the TOM and the Business Case before being incorporated into the design.
NEW QUESTION # 47
Which of below sentences best defines programme management?
- A. Executing dependent projects with aim of realizing benefits
- B. Action of carrying out coordinated organization, direction and implementation of project dossier and transformation activities to realize benefits of strategic importance
- C. Management of set of activities with dependencies and deadlines with aim of realizing benefits
- D. Coordinating projects under a common umbrella
Answer: B
Explanation:
Programme management is defined in MSP as "the action of carrying out coordinated organization, direction and implementation of project dossier and transformation activities to realize benefits of strategic importance." This definition underscores the holistic and strategic nature of programme management, integrating multiple projects and transformational efforts to deliver outcomes that align with organizational strategy.
The MSP Practitioner emphasizes the coordinated nature of programme management that differentiates it from project or portfolio management, focusing on realization of benefits through strategic change delivery.
This definition encapsulates the complexity and scope of programme management, ensuring delivery is both controlled and aligned to strategic goals.
NEW QUESTION # 48
For a programme that focuses on Political and societal change which scenario will lead to lower probability of success?
- A. Change to current legislation
- B. Long term societal effects
- C. Changes to public service delivery model
- D. New legislation reacting to societal trends
Answer: B
Explanation:
Programmes aimed at political and societal change face lower success probability when outcomes are vague or have long-term horizons that are difficult to define and measure. The MSP Practitioner explains: "Vaguely defined outcomes decrease probability of success." Long-term societal effects are often uncertain and harder to control, thus reducing the clarity needed for successful programme management and delivery.
NEW QUESTION # 49
Which of following is False?
- A. Stakeholder profiles are created under stakeholder maps
- B. Stakeholders can change during the lifecycle of programme
- C. Instead of having individual stakeholders, it is better to divide them in suitable categories
- D. Stakeholder profiles identifies and lists each stakeholder properties
Answer: A
Explanation:
The false statement is that "Stakeholder profiles are created under stakeholder maps." In fact, MSP treats the Stakeholder Map as a component or output of Stakeholder Profiling.
The MSP Practitioner explains: "Stakeholder map is created as part of stakeholder profile," meaning the profile contains detailed information about individual stakeholders, their attributes, influence, and interests, while the map visually represents stakeholder relationships and influence patterns.
This distinction is important for effective stakeholder analysis and engagement planning, ensuring both granular detail and strategic overview are captured.
NEW QUESTION # 50
Which of below sentences best defines programme management?
- A. Executing dependent projects with aim of realizing benefits
- B. Action of carrying out coordinated organization, direction and implementation of project dossier and transformation activities to realize benefits of strategic importance
- C. Management of set of activities with dependencies and deadlines with aim of realizing benefits
- D. Coordinating projects under a common umbrella
Answer: B
NEW QUESTION # 51
Which of the following statements is NOT TRUE?
- A. The Programme Manager is responsible for the Blueprint.
- B. The SRO is accountable for the Programme Brief.
- C. The SRO is accountable for confirming Programme Mandate.
- D. The Programme Manager is responsible for the Vision Statement.
Answer: C
Explanation:
The Sponsoring Group, not the SRO, is accountable for confirming the Programme Mandate. The MSP Practitioner clearly states: "The Sponsoring Group is accountable for confirming the mandate," which means the SRO oversees delivery but does not hold responsibility for initial mandate confirmation. Meanwhile, the Programme Manager has ownership of the Vision Statement and Blueprint, aligning with delivery responsibilities.
NEW QUESTION # 52
......